Mechwat has installed the BioToilet at various package of Mumbai Metro Line-3 and Mumbai International Airport Project under J Kumar Infra Projects Limited.

Detail Specification of BioToilet are as :

S.No. Features Detail
   
1 Size (W x D x H) in Ft. [(4 x 4 x 7)Ft.
2 Material to be used 24-12 mm Solid PVC Foam Sheet
3 Thickness of Sheet 24-12 mm PVC Foam Sheet
4 Moulded /Angle Channel based ? Angle Channel based
5 Urinal Type & Make Wall urinal, Hindustan make (Ceramic)
6 IWC MOC, Make Western/CERA Make
7 Flush Valve CP; Jaguar make
8 Electric work scope One LED lamp & switch board for  exhaust fan & lamp
9 Wash Basin  Included in each unit 9 inch size; Hindustan Make
10 Bio-digester Capacity 500 Liter
11 Maximum user for Biodigester 20 People per Day
12 Material of Bio-digester FRP; 10 mm thickness
13 Ventilation System 10 Inch Ventilation System ; Crompton make-3 set
14 Bio-inoculum 5 Kg
15 Bio-media Included in Biodigester
16 Health Faucet MOC : CP
17 Two Way  Bibcock SS ; Jaguar Make
18 Door 25 mm Square pipe along with 15 mm PVC Door & PVC Angle Frame.
19 Roofing 50  MM MS Square Pipe frame along with both Side 12mm sheet fitting
20 Water Tank& Stand Client’s Scope
21 Piping Work UPVC & PVC Piping Work
22 Installation work Biotoilet will be mounted on 100 mm PCC  Platform